Project Summary

The McArthur River project includes the fully developed McArthur River mine operation, being a currently idled underground mine operation, located in northern Saskatchewan, Canada approximately 620 km north of Saskatoon. Cameco has disclosed that the project is currently owned by a joint venture between Cameco (69.805%) and Orano (30.195%).

As of December 31, 2020, Cameco reported estimated: (i) proven and probable mineral reserves of 391.9 Mlbs of U3O8 at an average grade of 6.89% U3O8; and (ii) measured and indicated resources, exclusive of reserves, of 10.3 Mlbs at an average grade of 2.45% U3O8 and inferred resources of 2.6 Mlbs at an average grade of 2.85% U3O8. Cameco has stated that total packaged production at McArthur River from 2000 until it was placed on care and maintenance in 2018 was 325.4 Mlbs U3O8. Totaling historical production and all current reserves and resources, it has an attributable endowment of 730.2 Mlbs of U3O8, making the McArthur River uranium mine the world’s largest known high-grade uranium deposit.

Cameco has disclosed that McArthur River is the world’s largest high-grade uranium mine, with ore grades that are 100 times the world average, which means it is capable of producing 18 Mlbs per year by mining only 200 to 400 tonnes of ore per day. Cameco has disclosed that McArthur River has a licenced capacity of 25.0 Mlbs per year. Cameco estimated operating costs of $14.76 per pound for McArthur River based on operating and capital cost estimates for the estimated life of mine, stated in constant 2020 dollars and reflecting a forecast life of mine mill production of 389 Mlbs U3O8, including estimated milling costs. This would place McArthur River amongst the lowest cost uranium projects in the world.

The deposit is a high-grade, unconformity-related uranium deposit with an average stated grade of 6.89% U3O8 for remaining reserves disclosed by Cameco as of December 31, 2020. Mineralization occurs between 500 to 640 metres below surface with a strike length of approximately 1800 m.

Mining at McArthur River utilizes unique ground freezing to mitigate risks of high-pressure ground water and a blend of blasthole stoping and raise-bore mining. The ore is ground, thickened and blended into a slurry which is then shipped 80 km south to the Key Lake mill for processing and production of calcined uranium ore concentrate.  

Royalty Details

The McArthur River Royalty is a 1% GORR on a 9.063% share of uranium production from the McArthur River project derived from Orano’s current 30.195% production interest in the project. The royalty payor is Orano. The McArthur River Royalty includes an option for the holder to receive physical uranium as payment. Included in the royalty is the option to take physical uranium “in kind” with notice.

Uranium Royalty Corp. (“URC”) believes that the royalty covers the majority of the current project, with the exception of a portion of claims S-105655 and S-105656 of the currently defined McArthur River project lands. The McArthur River Royalty includes most of the area known as the McArthur River mine and URC believes that the royalty applies to the entirety of the reported reserves at the mine other than portions that are covered by the adjacent Read Lake project area. The McArthur Technical Report identified the reserves attributable to the Read Lake area as approximately 0.35 Mlbs, which represents approximately 0.09% of existing stated reserves for McArthur River.

Project History

The original joint venture established over the McArthur River area in 1976 was the Keefe-Henday joint venture between Canadian Kelvin Resources Ltd. and Asamera Oil Corporation Ltd. The Keefe Lake Joint Venture was later divided into three separate project areas, the Dawn Lake, McArthur River, and Waterbury Lake project areas. Cameco began construction and development of the McArthur River mine in 1997. Federal authorities issued the operating licence and mining began at the project in December 1999 and commercial production was achieved on November 1, 2000.

Cameco has disclosed that there have been two notable water inflow incidents at the McArthur River mine. The first occurred in April of 2003, as increased water inflow due to a rock fall in a new development area (Bay 12 located just above the 530-metre level) began to flood the lower portions of the mine, including the underground grinding circuit area. Cameco further disclosed that additional dewatering capacity was installed, and the flooded areas were dewatered and repaired, with mining resumed in July 2003, with the excess water inflow sealed off in July 2004. According to Cameco's disclosure, a second inflow occurred in November 2008, when there was a small water inflow in the lower Zone 4 development area on the 590-metre level, which did not impact production, but did delay local development for approximately one year. Cameco further disclosed that, in January 2010, the inflow was sealed off and local development was resumed. In 2013, federal authorities granted a 10-year renewal of the licenses for McArthur River and the Cameco operated Key Lake mill.

In addition to the resources outlined at the McArthur River Mine, several historical uranium deposits and showings have been discovered on the project. These include the P2 Main, BJ Lake, and Harrigan Zone deposits. These historical deposits do not have current resources attributed to them.

Recent Updates

Cameco disclosed that in 2018, a decision was made by the operator to suspend production at the mine and mill for an indeterminate duration. It further disclosed that a restart of the mine and mill is a commercial decision that will be based upon Cameco’s ability to commit its share of production from the operation under acceptable long-term contracts and to benefit from the favourable life of mine economics it provides.

The Cameco 2020 AIF states that it does not expect the operation to produce any uranium in 2021 and that Cameco’s share of the cash and non-cash costs to maintain both the McArthur River mine and associated Cameco operated Key Lake mill during the suspension is expected by it to range between $8 million and $10 million per month.

Note on Technical Disclosure

Unless otherwise indicated, the scientific and technical information herein regarding McArthur River has been derived from the technical report titled "McArthur River Operation, Northern Saskatchewan, Canada, National Instrument 43-101 Technical Report", with an effective date of December 31, 2018, prepared for Cameco, the Cameco 2020 AIF and Cameco's other public disclosures, copies of which are available under its profile on SEDAR, and historical uranium deposit information outlined in the Saskatchewan Mineral Deposit Index (SMDI).