• Project Summary
  • Royalty Description
  • Recent Updates
  • Project History

The Roughrider Project is a Development stage, conventional underground uranium project located in the eastern Athabasca Basin of northern Saskatchewan and is located approximately seven kilometres north of Points North Landing and covers an area of approximately 598 hectares. The Roughrider Project is 100% owned by a wholly-owned subsidiary of Uranium Energy Corporation. The royalties on the Roughrider project and Russell Lake and Russell Lake South projects are represented by the same royalty instrument. The Russell Lake projects are detailed in the following section.

The Roughrider Project was the flagship asset of Hathor Exploration Ltd. ("Hathor"), which Rio Tinto acquired for US$550 million between 2011 and 2012 pursuant to a competitive take-over bid that included a competing bid from Cameco.

On October 17, 2022, Uranium Energy Corporation (“UEC”) acquired the Roughrider Project from a subsidiary of Rio Tinto for total consideration of US$150 million comprised of US$80 million in cash and US$70 million in UEC shares.

Unless otherwise indicated, the scientific and technical information herein regarding the Roughrider Project has been derived from the S-K 1300 Technical Report Summary dated April 25, 2023, prepared for UEC and titled "Technical Report Summary: Roughrider Uranium Project, Saskatchewan, Canada" (the "Roughrider Technical Report Summary") and UEC's other public disclosures, copies of which are available under its profile on EDGAR and on SEDAR+.

On May 2, 2023, UEC announced completion of a Regulation S-K 1300 Technical Report Summary for the Roughrider project titled "The Roughrider Uranium Project, Saskatchewan, Canada" with an issued date of April 25, 2023, outlining 27.8 million lbs. U3O8 in 389,000 tonnes grading 3.25% U3O8 in the Indicated category and 36.0 million lbs. U3O8 in 359,000 tonnes grading 4.55% U3O8 in the Inferred category.

Mineral Resources – As of December 31, 2021 (100% Basis)
Measured Indicated Inferred
Tonnes
(Mt)
Grade
(% U3O8)
Content
(MLbs. U3O8)
Tonnes
(Mt)
Grade
(% U3O8)
Content
(MLbs. U3O8)
Tonnes
(Mt)
Grade
(% U3O8)
Content
(MLbs. U3O8)
      0.39 1.98 17.21 0.16 11.43 40.73
Notes on mineral resources:
  1. CIM Definition Standards have been followed for classification of mineral resources
  2. The cut-off grade of 0.05 percent U3O8 was used for the West Zone and 0.4 percent U3O8 was used for the East zone
  3. U3O8 price of US$80 per pound was assumed
  4. “Reasonable prospect for economic extraction” assumes open pit extraction for West Zone and underground extraction for East Zone and metallurgical recovery of 98%.
  5. Mineral resources are not mineral reserves and do not have demonstrated economic viability.
  6. Totals may not add correctly due to rounding.

 

The Company owns a 1.9766% NSR royalty on the Roughrider Project located in Saskatchewan, Canada (the "Roughrider Royalty"), payable pursuant to the interest that UEC or any of its subsidiaries, assignees or successors holds from time to time in the underlying property. For the Roughrider project, the royalty covers substantially all of the single Mineral Lease 5547 that overlies the Roughrider deposit. 

The Roughrider Royalty also applies to the Russell Lake and Russell Lake South projects, which are considered to be Early Exploration stage projects, located in the south-eastern rim of the Athabasca Basin. These projects are available for review in their own summary section. With the acquisition of the project from Rio Tinto, UEC is now the counterparty for the Roughrider royalty, but Rio Tinto currently remains the counterparty for the Russell Lake and Russell Lake South projects. 

In UEC's annual report on Form 10-K for the year ended July 31, 2023, UEC indicated that it is completing an updated economic assessment of the project, as well as camp infrastructure rehabilitation and upgrades. UEC further disclosed that it intends to complete additional resource delineation work during its fiscal year ending July 31, 2024 to further advance the project.

On May 2, 2023, UEC announced completion of a Regulation S-K 1300 Technical Report Summary for the Roughrider project titled "The Roughrider Uranium Project, Saskatchewan, Canada" with an issued date of April 25, 2023, outlining 27.8 million lbs. U3O8 in 389,000 tonnes grading 3.25% U3O8 in the Indicated category and 36.0 million lbs. U3O8 in 359,000 tonnes grading 4.55% U3O8 in the Inferred category.

UEC has also indicated the intention of completing an expanded Technical Report Summary including the economic parameters on the project in 2023. On May 23, 2023, the Company announced that it had selected consultants to conduct an initial assessment economic study under Regulation S-K1300 of the project and environmental baseline work for the project.

Historically the Roughrider project area has been explored by many different companies, often being incorporated in other neighboring project areas.  Between 1969 and 1974, following the discovery of the Rabbit Lake uranium deposit in 1968 by Gulf Minerals Ltd., Numac Oil and Gas held the large Permit Number Eight over the Midwest Lake (McMahon Lake) and Dawn Lake areas.

In 1976, Asamera Oil Corp. initiated the Dawn Lake project, located approximately 6 km southeast of the current Project. Asamera discovered the Dawn Lake 11, 11A, 11B, and 14 zones in 1978. In 1983, the Saskatchewan Mining and Development Corporation, predecessor to Cameco became the operator of the Dawn Lake Joint Venture. The Dawn Lake Joint Venture held the Esso North claim, which covered substantially all of the current Roughrider Project lease. During this same period, Asamera drilled 21 holes on the Esso North claim. Exploration on the Esso North claim was then dormant until 1995, when Cameco briefly reinitiated exploration before eventually allowing the claims to lapse in 2003.

Under an agreement dated September 10, 2004, between Roughrider Uranium Corp. (“Roughrider”) and Bullion Fund Inc. (“Bullion Fund”), Roughrider earned a 90% interest in claim S-107243, which covered substantially all the current Roughrider Project area. Bullion Fund retained a 10% carried interest. On August 10, 2006, Roughrider became a wholly owned subsidiary of Hathor Exploration Ltd. ("Hathor").

On April 12, 2007, Terra Ventures Inc. (“Terra”) announced that it had closed a deal with Bullion Fund to acquire an 8% carried working interest in seven claims comprising 56,360 acres in two separate projects located in the Athabasca Basin, Saskatchewan, of which 90% of the remaining 92% working interest was held by Hathor. One of the claims was S-107243. On March 24, 2008, Terra announced that it had closed its agreement with Bullion Fund to purchase Bullion Fund’s remaining 2% of Hathor’s carried working interest in the Project. This purchase increased Terra’s holding to a 10% carried working interest through to the completion of a feasibility study and the public announcement that the claims will be put into commercial production.

The Roughrider West zone was discovered by Hathor during the winter drilling program of February 2008. The Roughrider East zone was discovered during the summer drilling program in September 2009. A third zone, Roughrider Far East, was discovered during the winter drilling program in February 2011.

On April 18, 2011, Hathor and Terra announced that they had executed a binding letter agreement pursuant to which Hathor would acquire, in an all-share transaction, all the issued and outstanding shares of Terra. On August 5, 2011, Hathor and Terra announced the completion of the Arrangement and Terra became a wholly owned subsidiary of Hathor.

Hathor continued to develop the Roughrider Project, filing a historic technical report titled "Preliminary Economic Assessment Technical Report for the East and West Zones, Roughrider Uranium Project, Saskatchewan", with an effective date of September 13, 2011, prepared for Hathor (the "Historic Roughrider Technical Report"). The Historic Roughrider Technical Report included the Roughrider East Zone and Roughrider West Zone, in October of 2011. The Historic Roughrider Technical Report also included a preliminary economic assessment for the project (which Hathor announced the completion of in September 2011) which is not being treated as current by the Company.

In December 1, 2011, Rio Tinto announced that it was successful in acquiring Hathor, through a wholly owned Canadian subsidiary, Rio Tinto Canada Uranium Corp. (“RTCU”). On January 11, 2012, RTCU acquired all remaining Hathor common shares making RTCU 100% owners of the Project.

After acquiring the Roughrider Project, Rio Tinto continued to advance it. In July of 2013, Rio Tinto submitted an Advanced Exploration Program proposal for consideration to the Saskatchewan Ministry of Environment. The program was intended to initiate EIS review of the project, with the project intended to provide direct data related to the ore and mine development design. The proposal involved establishment of an upgraded access road, development of an exploration shaft, exploration drifts, operation of a water treatment facility, additional surface support structures, and temporary surface storage of both development rock and low-grade waste. The application was partially through the EIS review process, but no official determination was completed. (Saskatchewan Environment Publication 2013-014, “Rio Tinto – Roughrider Advanced Exploration Program”). In August of 2017, Rio Tinto announced that it had fully impaired the Roughrider asset.